A 42-task Gantt chart in Excel, built from the real NSW owner-builder chronological build order — not a generic project-builder template with the serial numbers filed off.

Why it runs longer than a builder's schedule

Most downloadable construction schedules assume a builder with trades booked back-to-back. You're queuing for the same subcontractors as everyone else, usually without a builder's standing relationships. This one starts from a realistic project-builder baseline per task, then applies an editable multiplier per task — heavier on real bottlenecks like brickwork, lighter on tasks you can do yourself whenever you have time, like painting or landscaping.

Owner-Builder

40 wks

Project-Builder Baseline

33 wks

Both are editable estimates in the spreadsheet, not fixed facts — replace the duration and multiplier for each task with real quotes as you get them.

Simplified stage view

The five stages below match the Build Roadmap. This bar simplifies the schedule into non-overlapping stage blocks for a big-picture read — the spreadsheet has the real, overlapping, task-by-task detail (42 tasks across 52 weeks) plus the mandatory NSW critical-stage inspections.

13w
6w
8w
6w
6w
  • 0 · Before You StartWeeks 113
  • 1 · Footings & SlabWeeks 1419
  • 2 · FrameWeeks 2027
  • 3 · Lock-upWeeks 2833
  • 4 · Fit-out & FinalWeeks 3439

What's in the spreadsheet

  • 0142 tasks in real chronological order, from permit lodgement to Occupation Certificate.
  • 02The 4 mandatory NSW critical-stage inspections, flagged and highlighted on the Gantt bars.
  • 03Two editable duration columns per task — a project-builder baseline and an owner-builder multiplier — so you can see exactly where your own build will run long.
  • 04A formula-driven Gantt: change a duration or multiplier and the whole schedule recalculates.
  • 05A Read Me tab documenting every source and assumption.

Preview the schedule

The real 42-task list below, read-only. Unlock full access to see live recalculation and download the editable .xlsx.

#TaskBuilder WksOB MultiplierCritical
0 · Before You Start
1Owner-Builder Permit lodged & approved (NSW Fair Trading)31×
2DA or CDC lodged & Construction Certificate issued81.2×
3Engage subcontractors & verify HBCF cover on any contract >$20k21.2×
4Order long-lead materials (trusses, frame package, windows)31.1×
5Services connection applications (water / power / sewer)21.1×
6Site survey & set-out0.51.1×
7Site clearing & preparation11.1×
8Temporary power & site water connected0.51×
9Long Service Levy paid (builds ≥$250k)0.51×
1 · Footings & Slab
10Excavate footings / slab11.2×
11Drainage under slab (stormwater / sewer)11.4×
12Termite protection installed0.51.2×
13Steel reinforcement placed in footings / slab11.3×
14CRITICAL INSPECTION — Steel / footings0.21.3×Inspection
15Pour concrete slab / footings0.51.2×
16Concrete curing before frame loads it1.51×
2 · Frame
17Wall frame erected1.51.3×
18Roof frame / trusses installed11.3×
19CRITICAL INSPECTION — Frame0.21.3×Inspection
20Roof covering installed (tiles / metal)1.51.3×
21External wall cladding / brickwork31.6×
22Windows & external doors installed11.2×
3 · Lock-up
23Building wrapped, flashings fitted11.2×
24Plumbing rough-in (wet areas)1.51.4×
25Electrical rough-in1.51.4×
26Other services rough-in (data, A/C, gas)11.3×
27Wet area waterproofing11.3×
28CRITICAL INSPECTION — Waterproofing0.21.3×Inspection
29Insulation installed0.51.1×
30Plasterboard & internal linings1.51.3×
4 · Fit-out & Final
31Internal painting — undercoat10.9×
32Cabinetry & joinery installed1.51.3×
33Tiling1.51.3×
34Final fix plumbing11.3×
35Final fix electrical11.3×
36Flooring (timber / carpet)1.51.2×
37Final painting10.9×
38Driveway / paths / external concrete11×
39Landscaping1.50.9×
40Final clean0.50.8×
41CRITICAL INSPECTION — Final0.21.3×Inspection
42Occupation Certificate issued0.51.1×
🔒 Planned Start/End Wk, live recalculation, and download — unlock for AUD $99

This is the real 42-task list, read-only. The paid version recalculates every task's start/end week live as you adjust durations and multipliers, plus gives you the editable .xlsx file itself.

Own this schedule for AUD $99, once